Skip to main content

v1.0

Major VersionM

Approved Installation Instruction Approval Process

by Todd Lucas

  1. The Base and Beam are oriented toward the Frame Front
    • The Base and Beam are oriented toward the Frame Front

    • Bolt the Bases to the Posts (Aligned Flush to Front).

    • Bolt the Beam to the Posts.

    • Erect the Frame Structure.

    • Level and Secure Frame Structure to the Floor.

    • Bolt the Supports to the Posts.

    • Plumb the Frame.

    • Secure the Supports to the Floor.

  2. Orient the Flush face of the Post with the Flush face of the Base.
    • Orient the Flush face of the Post with the Flush face of the Base.

    • Insert the Post into the square hole in the Base.

    • Install the bolts from the Frame Inside

    • through the Post

    • through the Base Flange.

    • Square the Post to the Base.

    • Secure them with a Lock Nut.

  3. Slide the Beam
    • Slide the Beam

    • between the Tabs on the Post Top.

    • Insert Bolts from the Front of the Frame.

    • Secure the pack with Lock Nuts.

  4. Move the Frame Structure to it's Installation Location.
    • Move the Frame Structure to it's Installation Location.

    • Level, Square and Plumb the Structure.

    • Anchor the Frame Structure to the Floor.

  5. Supports Bolt to the Outside of the Frame Structure Posts.
    • Supports Bolt to the Outside of the Frame Structure Posts.

    • With the Frame Plumb (Front to Back)

    • rest the Support's Floor Mounting Flange on the Floor

    • Bring the Mounting Angle of the Support to mate with the Outside Face, and the Rear Face of the Post

    • Bolt the Support to the Post.

    • Secure the Support to the Floor.

    • Repeat for the remaining support(s).

  6. Align the Edge of the First Section of Track
    • Align the Edge of the First Section of Track

    • with the Inside Face of the Post.

    • Align the Bottom Edge of the Track to the Bottom Edge of the Beam.

    • Check for Level.

    • Secure the First Section of Track to the Beam.

    • Butt the Second Section of Track up to the Edge of the First, then secure it to the the Beam.

    • The Last section of Track can be cut to the fill the remaining length to the other Post. (Cut the outermost end.)

Finish Line

Todd Lucas

Member since: 03/01/2022

13,056 Reputation

127 Guides authored

Team

Engineering Team Member of Engineering Team

3 Members

83 Guides authored

0 Comments

Add Comment

View Statistics:

Past 24 Hours: 1

Past 7 Days: 1

Past 30 Days: 1

All Time: 52