Measure the Opening Width near the top of the Opening.
-
Divide that overall width measurement in half to find the Centerline location.
-
Clearly Mark the Centerline location.
-
-
-
The Header Measuring Process is identical for all Door Models. The Door Model you are installing may be different from the Model shown.
-
Place the Door roll Header Assembly across a safe and level work surface, and rotate the roll assembly frame so that the Header Bracket Mounting flanges are facing upward.
-
Measure the total width of the whole roll assembly from outermost edge of one Header Bracket’s Mounting flange to the outermost edge of the opposite side.
-
Divide that number by 2. This number is 1/2 of the Header Width, and is used to determine the Header location on the Left and Right Sides of the opening.
-
-
-
Mark this dimension on each side of the Opening Center mark.
-
-
-
The Track Measuring Process is identical for all G1 Door Models. The Door Model you are installing may be different from the Model shown.
-
Set one of the Vertical Track Assemblies on your work surface.
-
Measure the Length of the Vinyl Track only.
-
ADD 3-1/4” to this number and take note.
-
This is the Height dimension needed to mark the location of the Bottom edge of the Header Mounting Brackets.
-
-
-
With the Calculated number (Track length + 3-1/4"), add a Horizontal line on each side of the Opening that intersects the previously drawn Vertical line.
-
-
-
Orient the slotted end of the Header Mounting Projection Bracket against the Mounting Surface.
-
Orient the flange outward.
-
Align the Bottom surface of the Header Mounting Bracket with the Horizontal line on the Mounting Surface.
-
Align the Outer edge of the Header Mounting Bracket with the Vertical line on the Mounting Surface.
-
Trace the slotted mounting slots onto the Mounting Surface.
-
-
-
Loosely fasten Bracket to the Mounting Surface with appropriate hardware.
-
Plumb the Bracket.
-
Tighten Hardware securely.
-
Repeat for the other Header Mounting Bracket.
-
-
-
Use two (2) people, and two ladders at minimum to Install the Roll Header Assembly.
-
Raise the Roll Header Assembly into place on the Projection Brackets.
-
Loosely tighten with three (3) sets of ¼-20 screws and hex nuts per side.
-
Do not fully tighten hardware until the Header Assembly Brackets are aligned with the Projection Bracket’s edges.
-
Check the Header Assembly for level, and make any necessary final adjustments.
-
Once aligned, fully tighten all six sets of hardware.
-
At this point leave the roll assembly tied off and held in place as it comes.
-
-
-
The Track Transition Bracket mounts to the Inside of the tab of the Header Assembly Mounting Bracket.
-
It is important to insert the Carriage Bolt from the inside of the Transition Bracket and the Washer and Hex Nut on the outside of the Header Bracket.
-
The Track must be plumb before securing it to the Mounting Surface.
-
-
-
Tracks are marked for orientation as Left Side, and Right Side.
-
Lay the two Vertical Track Assemblies on your work surface.
-
Un-roll the Side Seal material.
-
Remove the Plugs from the front of the Track
-
Locate the Track Projection Mount Brackets, four (4) per Track.
-
Locate four the ¼-20 Screws and Flanged Nuts.
-
-
-
Push a screw through the hole in the back surface from the inside of the Track.
-
Slip the Projection Bracket onto the 1/4-20 Screw, with the hole facing the Track, and then thread the nut, onto the screw.
-
The slotted end of the Projection Bracket will fasten to the Mounting Surface in a later step.
-
These Brackets should be Mounted so that their Flanges point Vertically (as shown).
-
Fully tighten the hardware for these brackets once they are aligned with the Track edges.
-
Re-install the Plug Caps into the hardware access holes on the front side of the Tracks.
-
-
-
The Track assembly mounts to the Inside of the Header Assembly Mounting Bracket.
-
From the inside of the Track, Insert the Carriage Bolt fully through the Square hole.
-
Then push the Carriage Bolt through the Header Bracket from the Inside.
-
Slide the Washer onto the Bolt from the outside of the Header Bracket , and snug the Hex Nut on the Bolt. (This Track Mount hardware will be removed in later steps.)
-
-
-
Plumb the Track Left to Right.
-
Transfer the Mounting Hole locations onto the Mounting Surface.
-
Remove the Track, and prepare these locations for Hardware appropriate to the Building Material.
-
Reinstall, snugly, the Track Mount Hardware. (It will be removed again in a later step.)
-
With the Track “hanging” in this position, Plumb the Track Left to Right.
-
Secure the Track Brackets to the Mounting Surface.
-
Tighten all of the Hardware Securely.
-
-
-
Remove the Track Mounting Hardware.
-
Re-Install the Hardware with the Side Seal Grommet under the Washer and Nut, then tighten Securely.
-
Affix the Hook and loop Material to the Header Bracket along the Top Edge of the Side Seal Material.
-
Fold and Secure the Side Seal Material to the Mounting Surface.
-
-
-
The top edge of the second lowest Wind Bar of the Door will be where the Lock Pin meets and holds the Door in the closed position. A factory-cut notch is located in the Door Panel, on the right-hand side, to allow the Lock Pin to pass through the Door.
-
Using the Pull Strap, pull the Door down/closed until a satisfactory seal with the floor is achieved.
-
Mark the location of the top edge of the second lowest Wind Bar onto the Right-Hand Door Track.
-
Release the Pull Strap to allow the door to return to the Open Position.
-
Drill a ¼” Dia. hole through both legs of the track 2” from the right (outside of the track) which intersects your line.
-
Drill a 3/16” hole, a few inches above the ¼” hole, at about ¾” from the right (outside of the Track).
-
Insert the Lanyard/cord through this hole, and tie a knot on that end.
-
To hold the Door in the Closed position: Pull the Door down to the closed position, and insert the Lock-Pin above the Wind Bar through the front and rear holes of the Door Track.
-
-
-
With the Door in the Open Position:
-
Pull the loose end of the long Strap through the Tie-off Bracket attached to the Right-Side Door Track.
-
Use the Buckle provided to secure the long Pull Strap to the loose end
-
Adjust the length to set the upper Stop Point of the Door.
-
-
-
Raise the Door to the fully Open position. This Unloads much, but NOT all, of the Spring Loading.
-
To fully Unload the Spring, with the Door raised, pull the Pin. The Shaft may spin inside as the Spring fully unloads.
-
Secure the Door Webbing to the Roll Tube to hold it in place during this process.
-
-
-
Spring tension is maintained either with a ½” open-end wrench on the wrench flats, or with the Quick-Release pin.
-
Spring tension is increased/decreased with a two-step process.
-
To increase spring tension, insert the open-end wrench onto the wrench flats and hold firmly
-
then pull the Quick-Release pin.
-
Pull the wrench down (CCW) until the pin can be replaced – about a quarter turn.
-
Repeat this two-step process about 8 times equaling about 2 full turns on the spring.
-
Release the ties on the Door Roll Assembly.
-
-
-
Pull the Door fully Closed, then release the Strap.
-
Note the Opening Stop Point.
-
Adjust the Opening Stop Point by increasing/decreasing the tension 1 quarter turn.
-
Test and adjust as needed.
-
Almost done!
Finish Line