  1. Tracks are marked for orientation as Left Side, and Right Side.
    • Tracks are marked for orientation as Left Side, and Right Side.

    • Lay the two Vertical Track Assemblies on your work surface.

    • Un-roll the Side Seal material.

    • Remove the Plugs from the front of the Track

    • Locate the Track Projection Mount Brackets, four (4) per Track.

    • Locate four the ΒΌ-20 Screws and Flanged Nuts.

  2. Push a screw through the hole in the back surface from the inside of the Track. Slip the Projection Bracket onto the 1/4-20 Screw, with the hole facing the Track, and then thread the nut, onto the screw.
    • Push a screw through the hole in the back surface from the inside of the Track.

    • Slip the Projection Bracket onto the 1/4-20 Screw, with the hole facing the Track, and then thread the nut, onto the screw.

    • The slotted end of the Projection Bracket will fasten to the Mounting Surface in a later step.

    • These Brackets should be Mounted so that their Flanges point Vertically (as shown).

    • Fully tighten the hardware for these brackets once they are aligned with the Track edges.

    • Re-install the Plug Caps into the hardware access holes on the front side of the Tracks.

Finish Line

Trent Borgardt

Member since: 03/01/2022

3,615 Reputation

57 Guides authored

Team

Engineering Team Member of Engineering Team

3 Members

83 Guides authored

0 Comments

Add Comment

View Statistics:

Past 24 Hours: 0

Past 7 Days: 0

Past 30 Days: 0

All Time: 48